wiki:docs/CommissioningPlan/P2.10

Version 2 (modified by kradhakrishnan, 3 years ago) (diff)

--

P2.10 Cryostat warm up check

  • Phase : 1
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C3)
  • Recurrence : at the end of every SHARK-NIR run?
  • Duration : 2 days

Description

  • Checking the cryostat warming up procedure.

Prerequisites

  • SHARK-NIR connected to LBT network.
  • Automatic logging of the cryostat temperature.

Procedure

  • Run the cryostat warm-up sequence.
  • Check how the system is performing every 30 minutes.

Templates

Success criteria

  • Cryostat warmed up without any issues.
  • The temperature at the detector is stable at dome temperature.

Notes

LBTO support

Date performed and by whom