P2.0B Installation of SHARK-NIR electronics on LBT platform

  • Phase : 2
  • Status : Draft
  • Category : Installation of SHARK-NIR at LBT platform (C2)
  • Recurrence : once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
  • Duration : 2 days.

Description

  • Installation of the electronics in the cabinets, cabling, and confirming the safety & security of the instrument and area.

Prerequisites

  • SHARK-NIR (main parts) are installed on the LBTO platform (activity P2.0A).

Procedure

  • Look at the AD4 document for the procedure and details.

Success criteria

  • SHARK-NIR electronics are successfully installed in the cabinets.
  • Connect all the cables and secure them.
  • Reassure all the connections, nuts, bolts, etc.
  • Confirm the safety and security of the instrument and the area.

Templates

Notes

  • Note that one (or two) rack(s) of the SHARK-NIR electronics are installed within the LBTO electronics cabinets (shared with LBTI and iLocater).
  • Input from Laura Funk (LBTO): Installation of the LBT platform takes around 4 hours and of course also its removal.

LBTO support

  • 1-2 crew members' support for the preparation and installation of SHARK-NIR electronics.
  • Safety officer
  • Kindly check the installation document, AD3, for more details

Date performed and by whom