v7 v8 5 5 - **Category** : Installation of SHARK-NIR at LBT platform (C2) 6 6 - **Recurrence** : once (unless deemed necessary to remove SHARK-NIR from the telescope platform) 7 - **Duration** : 2 days for preparation, 2 days for installation, and 1 day contingency.7 - **Duration** : 6 days 8 8 9 9 **Description**