P2.0A Installation of SHARK-NIR on LBT platform

  • Phase : 2
  • Status : Draft
  • Category : Installation of SHARK-NIR at LBT platform (C2)
  • Recurrence : once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
  • Duration : 6 days

Description

  • Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform.

Prerequisites

  • SHARK-NIR is aligned and ready for the lift-off.

Procedure

  • Look at the AD3 document for the procedure and details.

Templates

Success criteria

  • SHARK-NIR is successfully installed on the LBT platform.
  • Telescope is balanced.
  • Connect all the cables and secure them.
  • Reassure all the connections, nuts, bolts, etc.

Notes

  • Note that SHARK-NIR is NOT installed as a single piece. The cryostat has to be disassembled from the bearing before the installation can start. Please look into the AD3 document for details.
  • Input from Laura Funk (LBTO): Installation of the LBT work platform takes around 2 hours and of course also its removal. If the telescope installation is performed during the observing semester, carefully plan activities that can be completed so as not to interfere with handover for nighttime observations (~2 hours before sunset).

LBTO support

  • Crew members' support for the preparation, lift-off, and installation of SHARK-NIR
  • Crane operator (cleanroom, mountain bay, LBT platform)
  • Safety officer
  • Working platform installed in front of the Gregorian focal-station SX
  • Hatch door SX on the UIAP platform removed
  • Support for the installation of electronics in the LBTO cabinet
  • Kindly check the installation document, AD3, for more details

Date performed and by whom