P2.0 SHARK-NIR Open Cart Activities
- Phase : 2
- Status : Draft
- Category : Unpack, Assemble, Verification, and Installation (C1)
- Recurrence : once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
- Duration : 1 day
Description
- All activities to be done on the SHARK-NIR optical bench with the cart open.
Prerequisites
- electronics lab cleaned uup by LBTO
Procedure
- For each rotatory stage, PI116.DGH:
- put 2 drops of Rodorsil 47V500 oil on the shaft of the filter wheels, without dismounting anything. Make the mirror rotate completely a few times so that the oil distributes on the whole shaft.
- leave the C-RED2 ND filter wheel as last since it requires dismounting the folding mirror and the lens.
- Re-align tilt of both SCI filter wheels to eliminate ghosts from flat field images.
Success criteria
- All activities successfully completed and tested the proper functioning,
Notes
- Activity in the LBT Electronic room.
LBTO support
Associated SHARK-NIR personnel
Date performed and by whom Minimum number of people available from SN team: 2+1 SW. Comments Luca to provide detail on oil and method to be used, if needed.