  • docs/CommissioningPlan/P2.0

    v1 v2  
    1 You may download the installation plan (SHARK-NIR-INAFP-IP-001_Issue0.2.pdf) [here https://www.dropbox.com/home/SHARK-NIR/Released%20Docs/After%20FDR_do%20not%20update?preview=SHARK-NIR-INAFP-IP-001_Issue0.2.pdf]
     1== P2.0 Installation of SHARK-NIR at the LBT platform ==
     2•       **Phase**               :       2 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Installation, integration, verification (C1)                           
     5•       **Recurrence**  :       once (the Installation of SHARK-NIR at the LBT platform)
     6•       **Duration**            :       1 day for preparation, 1 day for installation , and 1 day contigency.
     7**Description**
     8•       Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform.
     9**Prerequisites**
     10•       SHARK-NIR aligned and ready for the lift-off.
     11**Procedure**
     12•       Look at [https://www.dropbox.com/home/SHARK-NIR/Released%20Docs/After%20FDR_do%20not%20update?preview=SHARK-NIR-INAFP-IP-001_Issue0.2.pdf this] document for the procedure and details.
     13**Success criteria**
     14•       SHARK-NIR successfully installed at the LBT platform.
     15•       Telescope is balanced.
     16•       Connect all the cables and secure them.
     17•       Reassure all the connections, nut and bolts etc.
     18**Notes**
     19**LBTO support**
     20•       crane operators, mountain crew support for the lift-off and installation.
     21**Associated SHARK-NIR personnel**
     22•       JF, LM, MdP, MM (from AZ)
     23**Date performed and by whom**