Version 16 (modified by elcarolo, 3 years ago) (diff) |
---|
P1.9 Internal tip-tilt loop verification
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, and Verification (C1)
- Recurrence : once at commissioning
- Duration : 1 day
Description
- Check the working of the internal tip-tilt loop using calibration unit light sources, C-RED2, and ALPAO-DM.
Prerequisites
- SCICAM cooled down.
Procedure
- Run the internal tip-tilt loop routine for different brightness of the source (star).
- Check its efficiency in keeping the PSF at the C-RED2 hot-pixel.
- Save data to the repository and analyze them.
Templates
- SHARKNIR_gen_tiptilt_loop (not released)
Success criteria
- Internal tip-tilt routine works fine and the PSF at the C-RED2 is stable within the required precision.
- All the data and analysis are saved in the repository.
Notes
LBTO support
- Liquid Nitrogen refill is required in the cleanroom.
Date performed and by whom