P1.9 Check the working of the internal tip-tilt loop

  • Phase : 2
  • Status : Draft
  • Category : Unpack, Assemble, and Verification (C1)???
  • Recurrence : once at commissioning
  • Duration : 1 day

Description

  • Check the working of the internal tip-tilt loop using calibration unit light sources, C-RED2, and ALPAO-DM.

Prerequisites

  • SCICAM cooled down.

Procedure

  • Run the internal tip-tilt loop routine for different brightness of the source (star).
  • Check its efficiency in keeping the PSF at the C-RED2 hot-pixel.
  • Save data to repository and analyze them.

Success criteria

  • Internal tip-tilt routine works fine and the PSF ar C-RED2 is stable within the required precision.
  • All the data and analysis saved in the repository.

Notes

LBTO support

  • Liquid Nitrogen refill is required in the cleanroom.

Associated SHARK-NIR personnel

Date performed and by whom

Comments