P1.9 Science detector calibrations
- Phase : 1
- Status : Draft
- Category : Installation, integration, verification (C1)
- Recurrence : once
- Duration : 1 hour(s)
Description
- Calibration of the SHARK-NIR science detector: Gain, bad pixels, read noise, linearity, dark current, flat field, cross-talk, persistence, pattern noise.
Prerequisites
- SHARK-NIR connected to LBT network.
- Electronics cabinets on.
- The cryostat should be running and cooled down.
- Internal alignment of the SHARK-NIR is verified.
Procedure
- A
- B
- c
Success criteria
- linearity as expected
- bad pixels mask created
- bias and flat took
Notes
- Save all the intermediate images for Dino to check the SHARK-NIR Data Reduction pipeline.
LBTO support Associated SHARK-NIR personnel
- JF, LM, MdP, MM (from AZ), Dino?
Date performed and by whom