    v13 v14  
    1  == P1.9        Check the working of the internal tip-tilt loop ==
    2 •       **Phase**               :       1
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Unpack, Assemble, and Verification (C1)
    5 •       **Recurrence**  :       once at commissioning
    6 •       **Duration**            :       1 day
     1 == P1.9        Internal tip-tilt loop verification ==
     2
     3- **Phase**             :       1
     4- **Status**            :       Draft   
     5- **Category**  :       Unpack, Assemble, and Verification (C1)
     6- **Recurrence**        :       once at commissioning
     7- **Duration**  :       1 day
     8
    79**Description**
    8 •       Check the working of the internal tip-tilt loop using calibration unit light sources, C-RED2, and ALPAO-DM.
     10- Check the working of the internal tip-tilt loop using calibration unit light sources, C-RED2, and ALPAO-DM.
    911
    1012**Prerequisites**
    11 •       SCICAM cooled down.
     13- SCICAM cooled down.
    1214
    1315**Procedure**
    14 •       Run the internal tip-tilt loop routine for different brightness of the source (star).
    15 * Check its efficiency in keeping the PSF at the C-RED2 hot-pixel.
    16 * Save data to the repository and analyze them.
     16- Run the internal tip-tilt loop routine for different brightness of the source (star).
     17- Check its efficiency in keeping the PSF at the C-RED2 hot-pixel.
     18- Save data to the repository and analyze them.
     19
     20**Templates**
    1721
    1822**Success criteria**
    19 * Internal tip-tilt routine works fine and the PSF ar C-RED2 is stable within the required precision.
    20 •       All the data and analysis are saved in the repository.
     23- Internal tip-tilt routine works fine and the PSF ar C-RED2 is stable within the required precision.
     24- All the data and analysis are saved in the repository.
     25
    2126**Notes**
    2227
    2328**LBTO support**
    24 * Liquid Nitrogen refill is required in the cleanroom.
    25 **Associated SHARK-NIR personnel**
     29- Liquid Nitrogen refill is required in the cleanroom.
    2630
    2731**Date performed and by whom**
    28 
    29 **Comments**