wiki:docs/CommissioningPlan/P1.8

Version 4 (modified by kradhakrishnan, 4 years ago) (diff)

--

P1.8 Verification of the internal alignment of the instrument

  • Phase : 1
  • Status : Draft
  • Category : Unpack, Assemble, Verification, and Installation (C1)
  • Recurrence : once
  • Duration : 4 days

Description

  • Check the internal alignment of the SHARK-NIR using the light sources within.

Prerequisites

  • SHARK-NIR connected to LBT network.
  • Electronics cabinets on.
  • The cryostat should be running and cooled down.

Procedure

  • Use the on-axis calibration fiber and checking if the spot position on the scientific detector is consistent with the one recorded before shipping for multiple bearing angles.
  • Check the pupil position at the detector and verify the consistency with the one before shipping.
  • Check the relative alignment of the coronographic masks.
  • Verify the contrast obtained for different sets of masks on the scientific camera and compare it with the values before shipping.
  • If necessary, re-align the optical bench internally (this is not anticipated, and the time above does not consider this).

Success criteria

  • The on-axis spot at the SCICAM is where it should be across the bearing rotation?
  • Use pupil images and compare?
  • PSF quality across?

Notes

LBTO support

Associated SHARK-NIR personnel

Date performed and by whom