     1== P1.8 Verification of the internal alignment of the instrument ==
     2•       **Phase**               :       1 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Installation, integration, verification (C1)
     5•       **Recurrence**  :       once
     6•       **Duration**            :       2 hour(s)
     7**Description**
     8•       Check the internal alignment of the SHARK-NIR using the light sources within.
     9**Prerequisites**
     10•       SHARK-NIR connected to LBT network.
     11•       Electronics cabinets on.
     12•       The cryostat should be running and cooled down.
     13**Procedure**
     14•       Use the on-axis calibration fiber and checking if the spot position on the scientific detector is consistent with the one recorded before shipping for multiple bearing angles.
     15•       Check the pupil position at the detector and verify the consistency with the one before shipping.
     16•       Check the relative alignment of the coronographic masks
     17•       Verify the contrast obtained for different sets of masks on the scientific camera and compare it with the values before shipping.
     18•       If necessary, re-align the optical bench internally.
     19**Success criteria**
     20•       The on-axis spot at the SCICAM is where it should be across the bearing rotation?
     21•       Use pupil images and compare?
     22•       PSF quality across?
     23**Notes**
     24**LBTO support**
     25**Associated SHARK-NIR personnel**
     26•       JF, LM, MdP,
     27**Date performed and by whom**