    11== P1.7 Motor/light sources functional verification and filter artifacts/defects verification ==
    2 •       **Phase**               :       1 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Unpack, Assemble, and Verification (C1)
    5 •       **Recurrence**  :       once
    6 •       **Duration**            :       1.5
     2
     3- **Phase**             :       1 
     4- **Status**            :       Draft   
     5- **Category**  :       Unpack, Assemble, and Verification (C1)
     6- **Recurrence**        :       once
     7- **Duration**  :       1.5
     8
    79**Description**
    8 •       Checking the working of motors and light sources within SHARK-NIR using optical feedback. Finding the filter defects/artifacts using an internal calibration source (flat-field) within the instrument.
     10- Checking the working of motors and light sources within SHARK-NIR using optical feedback. Finding the filter defects/artefacts using an internal calibration source (flat-field) within the instrument.
     11
    912**Prerequisites**
    10 •       SHARK-NIR connected to LBT network.
    11 •       Electronics racks on.
    12 •       DM best shape uploaded (shape minimizing internal aberrations)
    13 •       The cryostat should be running and cooled down.
     13- SHARK-NIR connected to LBT network.
     14- Electronics racks on.
     15- DM best shape uploaded (shape minimizing internal aberrations)
     16- The cryostat should be running and cooled down.
     17
    1418**Procedure**
    15 •       When the services are up and running, after the motors are homed, each of the individual motors is individually tested for their different named/nominal positions.
    16 •       The light sources within SHARK-NIR are used simultaneously to check the working of the motors looking at the optical feedback.
    17 * Check the CRED-2 and ALPAO-DM SW and optical feedback.
    18 * Take the images of all the filters using the internal calibration source (flat-field) within the instrument to locate/find out the filter defects/artifacts, if any. You may take short- and long-exposures to get better contrast of the features if required.
    19 * Check the filter wheel position monitoring script detailed in [wiki:/docs/Commissioning/SNM1 SNM1]. Save the data in the repository.
     19- When the services are up and running, after the motors are homed, each of the individual motors is individually tested for their different named/nominal positions.
     20- The light sources within SHARK-NIR are used simultaneously to check the working of the motors looking at the optical feedback.
     21- Check the CRED-2 and ALPAO-DM SW and optical feedback.
     22- Take the images of all the filters using the internal calibration source (flat-field) within the instrument to locate/find out the filter defects/artefacts, if any. You may take short- and long-exposures to get better contrast of the features if required.
     23- Check the filter wheel position monitoring script detailed in [wiki:/docs/Commissioning/SNM1 SNM1]. Save the data in the repository.
     24
     25**Templates**
    2026
    2127**Success criteria**
    22 •       All the motors can reach the named positions / nominal positions.
    23 •       All the light sources are working and confirmed through optical feedback at the SCICAM.
    24 * Filter wheel position monitoring script is run successfully and data saved in the repository.
    25 * CRED-2 AND ALPAO-DM working normally.
    26 •       All the filter images saved.
     28- All the motors can reach the named positions / nominal positions.
     29- All the light sources are working and confirmed through optical feedback at the SCICAM.
     30- Filter wheel position monitoring script is run successfully and data is saved in the repository.
     31- CRED-2 AND ALPAO-DM working normally.
     32- All the filter images are saved.
    2733
    2834**Notes**
    2935
    30 **Templates**
    31 -
    32 
    3336**LBTO support**
    34 * Liquid Nitrogen refill is required in the cleanroom.
    35 **Associated SHARK-NIR personnel**
     37- Liquid Nitrogen refill is required in the cleanroom.
    3638
    3739**Date performed and by whom**
    38 
    39 
    40 **Comments**