     1== P1.7 Verification of the operability of the motors and light sources ==
     2•       **Phase**               :       1 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Installation, integration, verification (C1)                           
     5•       **Recurrence**  :       once
     6•       **Duration**            :       1 hour(s)
     7**Description**
     8•       Checking the working of motors and light sources within SHARK-NIR
     9**Prerequisites**
     10•       SHARK-NIR connected to LBT network.
     11•       Electronics cabinets on.
     12•       The cryostat should be running and cooled down.
     13**Procedure**
     14•       When the services are up and running, after the motors are homed, each of the individual motors is individually tested for their different named/nominal positions.
     15•       The light sources within SHARK-NIR may be used simultaneously to check the working of the motors looking at the optical feedback.
     16**Success criteria**
     17•       All the motors can reach their software limits, named positions / nominal positions.
     18•       All the light sources are working and confirmed through optical feedback at the SCICAM.
     19**Notes**
     20**LBTO support**
     21**Associated SHARK-NIR personnel**
     22•       JF, LM, MdP,
     23**Date performed and by whom**