| 1 | == P1.7 Verification of the operability of the motors and light sources == |
| 2 | • **Phase** : 1 |
| 3 | • **Status** : Draft |
| 4 | • **Category** : Installation, integration, verification (C1) |
| 5 | • **Recurrence** : once |
| 6 | • **Duration** : 1 hour(s) |
| 7 | **Description** |
| 8 | • Checking the working of motors and light sources within SHARK-NIR |
| 9 | **Prerequisites** |
| 10 | • SHARK-NIR connected to LBT network. |
| 11 | • Electronics cabinets on. |
| 12 | • The cryostat should be running and cooled down. |
| 13 | **Procedure** |
| 14 | • When the services are up and running, after the motors are homed, each of the individual motors is individually tested for their different named/nominal positions. |
| 15 | • The light sources within SHARK-NIR may be used simultaneously to check the working of the motors looking at the optical feedback. |
| 16 | **Success criteria** |
| 17 | • All the motors can reach their software limits, named positions / nominal positions. |
| 18 | • All the light sources are working and confirmed through optical feedback at the SCICAM. |
| 19 | **Notes** |
| 20 | **LBTO support** |
| 21 | **Associated SHARK-NIR personnel** |
| 22 | • JF, LM, MdP, |
| 23 | **Date performed and by whom** |