P1.7 Verification of the operability of the motors and light sources

  • Phase : 1
  • Status : Draft
  • Category : Installation, integration, verification (C1)
  • Recurrence : once
  • Duration : 1 hour(s)

Description

  • Checking the working of motors and light sources within SHARK-NIR

Prerequisites

  • SHARK-NIR connected to LBT network.
  • Electronics cabinets on.
  • The cryostat should be running and cooled down.

Procedure

  • When the services are up and running, after the motors are homed, each of the individual motors is individually tested for their different named/nominal positions.
  • The light sources within SHARK-NIR may be used simultaneously to check the working of the motors looking at the optical feedback.

Success criteria

  • All the motors can reach their software limits, named positions / nominal positions.
  • All the light sources are working and confirmed through optical feedback at the SCICAM.

Notes LBTO support Associated SHARK-NIR personnel

  • JF, LM, MdP,

Date performed and by whom