P1.6 SCICAM refocussing
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, and Verification (C1)
- Recurrence : once
- Duration : 1.5 day
Description
- The SCICAM of the SHARK-NIR is believed to be not in-focus position. The detector team at Steward Observatory will have the cryostat at an early stage (prior to SHARK-NIR arriving at LBT) to look into several aspects including the focussing issue. Depending on the outcome of this intervention, refocussing of the cryostat is anticipated.
Prerequisites
- SHARK-NIR is connected to the LBT network.
- Electronics cabinets on.
- Steward Observatory Detector Team has completed the work and the information is passed on to the SHARK-NIR team.
- Cryostat cooled down.
Procedure
- Mount the cryostat to the SHARK-NIR optical bench.
- Use several shims one after the other to take images at the detector.
- Using the through-focus images, find the right shim to have the detector at the focus position.
- Make the shim of the right dimensions.
- Use this shim, and mount the cryostat to the SHARK-NIR optical bench.
- Verify that the final configuration produces focused images.
Templates
Success criteria
- SCICAM is focused.
Notes
LBTO support
- Support to use of the workshop at LBT.
Date performed and by whom