P1.6 Cryostat cool down
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, and Verification (C1)
- Recurrence : once
- Duration : 0.5 day
Description
- Cooldown the cryostat.
Prerequisites
- SHARK-NIR connected to LBT network.
- Electronics cabinets on.
- Needs vacuum pumping at the beginning (vacuum pressure of 10e-5 Torr is good (see the cryostat manual SHARK-NIR_SO-MAN-001)).
Procedure
- Start the cryostat cooling down sequence (see the cryostat manual SHARK-NIR_SO-MAN-001).
- Check how the system performance every 30 minutes.
Templates
Success criteria
- Cryostat cooled down without any issues.
- The temperature at the detector is stable at ~78K.
Notes
- This activity can run in parallel with other cleanroom activities (which do not need a cold detector).
LBTO support
- Liquid Nitrogen refill is required in the cleanroom.
- Vacuum pump and support for cooling down the cryostat.
Date performed and by whom