P1.6 Cool down the cryostat

  • Phase : 1
  • Status : Draft
  • Category : Unpack, Assemble, Verification, and Installation (C1)
  • Recurrence : once
  • Duration : 1 day

Description

  • Cooldown the cryostat.

Prerequisites

  • SHARK-NIR connected to LBT network.
  • Electronics cabinets on.
  • Needs vacuum pumping at the beginning (vacuum pressure of 10e-5 Torr is good (see the cryostat manual SHARK-NIR_SO-MAN-001).
  • Liquid nitrogen pumped?

Procedure

  • Start the cryostat cooling down sequence (see the cryostat manual SHARK-NIR_SO-MAN-001).
  • Check how the system is performing every 30 minutes

Success criteria

  • Cryostat cooled down without any issues.
  • The temperature at the detector is stable at 77K

Notes

LBTO support

  • Liquid Nitrogen refill is required in the cleanroom.
  • Vacuum pump and support for cooling down the cryostat.

Associated SHARK-NIR personnel

Date performed and by whom

Comments LM: I do not see liquid nitrogen pumped as a prerequisite, but rather part of the procedure