docs/CommissioningPlan/P1.6
v8 v9 10 10 • SHARK-NIR connected to LBT network. 11 11 • Electronics cabinets on. 12 • Needs vacuum pumping at the beginning (vacuum pressure of 10e-5 is good (see the cryostat manual SHARK-NIR_SO-MAN-001).12 • Needs vacuum pumping at the beginning (vacuum pressure of 10e-5 Torr is good (see the cryostat manual SHARK-NIR_SO-MAN-001). 13 13 • Liquid nitrogen pumped? 14 14 **Procedure**