Changes between Version 2 and Version 3 of docs/CommissioningPlan/P1.6
- Timestamp:
- 01/15/21 15:07:30 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P1.6
v2 v3 2 2 • **Phase** : 1 3 3 • **Status** : Draft 4 • **Category** : Installation, integration, verification (C1)4 • **Category** : Unpack, Assemble, Verification, and Installation (C1) 5 5 • **Recurrence** : once 6 • **Duration** : 8 hour(s)6 • **Duration** : 1 day 7 7 **Description** 8 8 • Cooldown the cryostat. … … 17 17 **Success criteria** 18 18 • Cryostat cooled down without any issues. 19 • The temperature at the detector is stable at 77K ?19 • The temperature at the detector is stable at 77K 20 20 **Notes** 21 21 **LBTO support** 22 22 • Liquid Nitrogen refill. Note that we do not mention about Liquid Nitrogen refill in any other place. This has to be done periodically every 24 hours. 23 23 **Associated SHARK-NIR personnel** 24 • JF, LM, MdP, MM(from AZ) 24 25 25 **Date performed and by whom**