    1 == P1.6 Cool down the cryostat  ==
    2 •       **Phase**               :       1 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Unpack, Assemble, and Verification (C1)
    5 •       **Recurrence**  :       once
    6 •       **Duration**            :       1 day
     1== P1.6 Cryostat cool down  ==
     2
     3- **Phase**             :       1 
     4- **Status**            :       Draft   
     5- **Category**  :       Unpack, Assemble, and Verification (C1)
     6- **Recurrence**        :       once
     7- **Duration**  :       1 day
     8
    79**Description**
    8 •       Cooldown the cryostat.
     10- Cooldown the cryostat.
     11
    912**Prerequisites**
    10 •       SHARK-NIR connected to LBT network.
    11 •       Electronics cabinets on.
    12 •       Needs vacuum pumping at the beginning (vacuum pressure of 10e-5 Torr is good (see the cryostat manual SHARK-NIR_SO-MAN-001)).
     13- SHARK-NIR connected to LBT network.
     14- Electronics cabinets on.
     15- Needs vacuum pumping at the beginning (vacuum pressure of 10e-5 Torr is good (see the cryostat manual SHARK-NIR_SO-MAN-001)).
     16
    1317**Procedure**
    14 •       Start the cryostat cooling down sequence (see the cryostat manual SHARK-NIR_SO-MAN-001).
    15 •       Check how the system is performing every 30 minutes.
    16 **Success criteria**
    17 •       Cryostat cooled down without any issues.
    18 •       The temperature at the detector is stable at ~78K.
    19 **Notes**
    20 * This activity can run in parallel with other cleanroom activities (which do not need a cold detector).
     18- Start the cryostat cooling down sequence (see the cryostat manual SHARK-NIR_SO-MAN-001).
     19- Check how the system is performing every 30 minutes.
    2120
    2221**Templates**
    23 -
     22
     23**Success criteria**
     24- Cryostat cooled down without any issues.
     25- The temperature at the detector is stable at ~78K.
     26
     27**Notes**
     28- This activity can run in parallel with other cleanroom activities (which do not need a cold detector).
    2429
    2530**LBTO support**
    26 •       Liquid Nitrogen refill is required in the cleanroom.
    27 * Vacuum pump and support for cooling down the cryostat.
    28 **Associated SHARK-NIR personnel**
     31- Liquid Nitrogen refill is required in the cleanroom.
     32- Vacuum pump and support for cooling down the cryostat.
    2933
    3034**Date performed and by whom**
    31 
    32 **Comments**