Changes between Version 14 and Version 15 of docs/CommissioningPlan/P1.6


Ignore:
Timestamp:
02/03/21 11:48:30 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P1.6

    v14 v15  
    1313**Procedure**
    1414•       Start the cryostat cooling down sequence (see the cryostat manual SHARK-NIR_SO-MAN-001).
    15 •       Check how the system is performing every 30 minutes
     15•       Check how the system is performing every 30 minutes.
    1616**Success criteria**
    1717•       Cryostat cooled down without any issues.
    18 •       The temperature at the detector is stable at 77K
     18•       The temperature at the detector is stable at 77K.
    1919**Notes**
    2020* This activity can run in parallel with other cleanroom activities (which do not need a cold detector).
     
    2828
    2929**Comments**
    30 * LM: I do not see liquid nitrogen pumped as a prerequisite, but rather part of the procedure [DONE]