     1== P1.5 Start all the services and initialize all the motors ==
     2•       **Phase**               :       1 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Installation, integration, verification (C1)                           
     5•       **Recurrence**  :       once
     6•       **Duration**            :       20 minutes
     7**Description**
     8•       When the electronics cabinets are switched on, verify individual services working and initialize the motors to nominal positions.
     9**Prerequisites**
     10•       SHARK-NIR connected to LBT network.
     11•       Electronics cabinets on.
     12•       A script to initialize the motors.
     13**Procedure**
     14•       Switch on the electronics cabinets and individual components.
     15•       Start individual services.
     16•       Initialize every motor (possibly by running a script).
     17**Success criteria**
     18•       All the services are up and running with no fatal errors and understand the errors or warnings if any.
     19•       All the motors are working, initialized, and sent to the nominal positions.
     20**Notes**
     21**LBTO support**
     22**Associated SHARK-NIR personnel**
     23•       JF, LM, MdP,
     24**Date performed and by whom**