P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, Verification, and Installation (C1)
- Recurrence : once
- Duration : half a day
Description
- At the LBT clean room, cable in the instrument. Power on the cabinets, install workstations, and connect SHARK-NIR to LBT network.
Prerequisites
- All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to LBT network.
Procedure
- Carefully cable in SHARK-NIR.
- Switch on the electronics cabinets.
- Install the instrument workstation in the server room and scientific camera workstation in control room level 2.
- Install the scientific camera workstation in control room level 2.
- Connect SHARK-NIR to the LBT network.
Success criteria
- Electronics cabinets are powered on (working of led lights, fans, etc.).
- SHARK-NIR can be accessed through LBT network (e.g. Switching on/off services remotely from the control room).
Notes LBTO support
- IT Support to connect to the LBT network.
- Any electronics support needed?
Associated SHARK-NIR personnel
Date performed and by whom
Attachments (1)
- SHARK-NIR_Computer_Structure.png (101.2 KB) - added by kradhakrishnan 3 years ago.