wiki:docs/CommissioningPlan/P1.4

Version 2 (modified by kradhakrishnan, 4 years ago) (diff)

--

P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network

  • Phase : 1
  • Status : Draft
  • Category : Installation, integration, verification (C1)
  • Recurrence : once
  • Duration : 2 hour(s)

Description

  • At the LBT clean room, cable in the instrument. Power on the cabinets,install workstations, and connect SHARK-NIR to LBT network.

Prerequisites

  • All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to LBT network.

Procedure

  • Carefully cable in SHARK-NIR.
  • Switch on the electronics cabinets.
  • Install the instrument workstation in the server room and scientific camera workstation in control room level 2
  • Install the scientific camera workstation in control room level 2
  • Connect SHARK-NIR to the LBT network.

Success criteria

  • Electronics cabinets are powered on (working of led lights, fans, etc.).
  • SHARK-NIR can be accessed through LBT network (e.g. Switching on/off services remotely from the control room).

Notes LBTO support

  • IT Support to connect to the LBT network.
  • Any electronics support needed?

Associated SHARK-NIR personnel

  • JF, LM, MdP,

Date performed and by whom