Version 21 (modified by kradhakrishnan, 3 years ago) (diff) |
---|
P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, and Verification (C1)
- Recurrence : once
- Duration : 1 day
Description
- At the LBT clean room, cable in the instrument. Power on the electronics, install workstations (in the server room) and connect SHARK-NIR to the LBT network.
Prerequisites
- Presence of all the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to the LBT network.
Procedure
- Carefully cable in SHARK-NIR.
- Switch on the electronics.
- Install the instrument workstation (and its copy/backup) and the scientific camera (SCICAM) workstation in the server room.
- Connect SHARK-NIR to the LBT network.
- Ready essential laptops ready with all the relevant software for the cleanroom activity. Check the connection with both the workstations mentioned earlier.
Templates
Success criteria
- Electronics is powered on (working of led lights, fans, etc.).
- SHARK-NIR can be accessed through the LBT network (e.g. Switching on/off services remotely from the control room).
Notes
- SCICAM is redundant with other SCICAM computers inside of LBTI. There will not be a separate SCICAM workstation copy/backup.
LBTO support
- Need 2 free and accessible network ports to connect (a) the SHARK-NIR instrument network switch to the LBTO network, and (b) a working laptop/computer to the LBTO network.
- IT support to install/set the workstations in the proper location, connect to the LBT network.
- At the server room, we need 6 free network ports to connect SHARKNIRWS, SHARKNIRWS2, SASHAWS to the LBTO network. Also, we need 6 free standard electric plugs.
- LBTO SW support may be needed.
Date performed and by whom