docs/CommissioningPlan/P1.4
v3 v4 6 6 • **Duration** : half a day 7 7 **Description** 8 • At the LBT clean room, cable in the instrument. Power on the cabinets, install workstations , and connect SHARK-NIR toLBT network.8 • At the LBT clean room, cable in the instrument. Power on the cabinets, install workstations and connect SHARK-NIR to the LBT network. 9 9 **Prerequisites** 10 • All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to LBT network.10 • All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to the LBT network. 11 11 **Procedure** 12 12 • Carefully cable in SHARK-NIR. … … 17 17 **Success criteria** 18 18 • Electronics cabinets are powered on (working of led lights, fans, etc.). 19 • SHARK-NIR can be accessed through LBT network (e.g. Switching on/off services remotely from the control room).19 • SHARK-NIR can be accessed through the LBT network (e.g. Switching on/off services remotely from the control room). 20 20 **Notes** 21 21 22 **LBTO support** 22 23 • IT Support to connect to the LBT network.