Changes between Version 23 and Version 24 of docs/CommissioningPlan/P1.4
- Timestamp:
- 02/14/22 15:14:58 (3 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P1.4
v23 v24 32 32 - IT support to install/set the workstations in the proper location, connect to the LBT network. 33 33 - At the server room, we need 6 free network ports to connect SHARKNIRWS, SHARKNIRWS2, SASHAWS to the LBTO network. Also, we need 6 free standard electric plugs. 34 - At the cleanroom, we will need 1 power plug for the surge suppressor, and the maximum expected load will be of the order of 880W. Our PDUs connected to the surge suppressor. Also, couple of other normal power plugs for connecting laptops, monitors, etc. An extension power strip, if available, will be good. 34 35 - LBTO SW support may be needed. 35 36