wiki:docs/CommissioningPlan/P1.4

Version 23 (modified by kradhakrishnan, 3 years ago) (diff)

--

P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network

  • Phase : 1
  • Status : Draft
  • Category : Unpack, Assemble, and Verification (C1)
  • Recurrence : once
  • Duration : 1 day

Description

  • At the LBT clean room, cable in the instrument. Power on the electronics, install workstations (in the server room) and connect SHARK-NIR to the LBT network.

Prerequisites

  • Presence of all the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to the LBT network.

Procedure

  • Carefully cable in SHARK-NIR.
  • Switch on the electronics.
  • Install the instrument workstation (and its copy/backup) and the scientific camera (SCICAM) workstation in the server room.
  • Connect SHARK-NIR to the LBT network.
  • Ready essential laptops ready with all the relevant software for the cleanroom activity. Check the connection with both the workstations mentioned earlier.

Templates

Success criteria

  • Electronics is powered on (working of led lights, fans, etc.).
  • SHARK-NIR can be accessed through the LBT network (e.g. Switching on/off services remotely from the control room).

Notes

  • SCICAM is redundant with other SCICAM computers inside of LBTI. There will not be a separate SCICAM workstation copy/backup.

LBTO support

  • Need 2 free and accessible network ports to connect (a) the SHARK-NIR instrument network switch to the LBTO network, and (b) a working laptop/computer to the LBTO network.
  • IT support to install/set the workstations in the proper location, connect to the LBT network.
  • At the server room, we need 6 free network ports to connect SHARKNIRWS, SHARKNIRWS2, SASHAWS to the LBTO network. Also, we need 6 free standard electric plugs.
  • LBTO SW support may be needed.