Changes between Version 6 and Version 7 of docs/CommissioningPlan/P1.3
- Timestamp:
- 01/25/21 12:56:31 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P1.3
v6 v7 12 12 • Carefully assemble and integrate the various opto-mechanical components. 13 13 • Install them one by one onto the mechanical structure (either at mountain bay or at the cleanroom). 14 * Before installing the motor electronics rack in the cleanroom, take it to the LBT Platform cabinet (its final destination) shared with iLocator for sanity checks. 14 15 • Install the electronics cabinet. 15 16 **Success criteria** … … 21 22 • Crane operator to lift and move stuff. 22 23 • 1-2 crew to support installation on the mechanical structure. 24 * Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed. 23 25 **Associated SHARK-NIR personnel** 24 26