    1 == P1.3 Complete the installation of SHARK-NIR in the cleanroom with its electronics cabinet ==
    2 •       **Phase**               :       1 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Unpack, Assemble, and Verification (C1)
    5 •       **Recurrence**  :       once
    6 •       **Duration**            :       1.5 day
     1== P1.3 Installation of SHARK-NIR HW and electronics in clean room ==
     2- **Phase** :   1 
     3- **Status** :  Draft   
     4- **Category** :        Unpack, Assemble, and Verification (C1)
     5- **Recurrence** :      once
     6- **Duration** :        1.5 day
    77**Description**
    8 •       Install and integrate the different SHARK-NIR opto-mechanical components onto the mechanical structure. Install the electronics cabinets. Move the unit to the cleanroom.
     8- Install and integrate the different SHARK-NIR opto-mechanical components onto the mechanical structure. Install the electronics cabinets. Move the unit to the cleanroom.
    99**Prerequisites**
    10 •       All the necessary tools and safety features to do the installation, integration, and moving to the cleanroom. The mechanical structure to hold SHARK-NIR at the cleanroom should be assembled and ready to be used (with the possibility to move to the cleanroom).
     10- All the necessary tools and safety features to do the installation, integration, and moving to the cleanroom. The mechanical structure to hold SHARK-NIR at the cleanroom should be assembled and ready to be used (with the possibility to move to the cleanroom).
    1111**Procedure**
    12 •       Carefully integrate the cryostat unit with the derotator-optical bench unit.
    13 * Before installing the motor electronics rack in the cleanroom, take it to the LBT Platform cabinet (its final destination) shared with iLocater for sanity checks.
    14 •       Set up the electronics racks.
     12- Carefully integrate the cryostat unit with the derotator-optical bench unit.
     13- Before installing the motor electronics rack in the cleanroom, take it to the LBT Platform cabinet (its final destination) shared with iLocater for sanity checks.
     14- Set up the electronics racks.
     15**Templates**
     16
    1517**Success criteria**
    16 •       The SHARK-NIR is primarily assembled on to the mechanical structure.
    17 •       Electronics racks are set up and ready to use.
     18- The SHARK-NIR is primarily assembled on to the mechanical structure.
     19- Electronics racks are set up and ready to use.
    1820**Notes**
    1921
    2022**LBTO support**
    21 •       Crane operator to lift and move stuff (mountain bay and/or cleanroom).
    22 •       1-2 crew to support installation procedure (mountain bay and/or cleanroom).
    23 * Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed.
    24 * Optical bench and access to the clean tent.
    25 **Associated SHARK-NIR personnel**
     23- Crane operator to lift and move stuff (mountain bay and/or cleanroom).
     24- 1-2 crew to support installation procedure (mountain bay and/or cleanroom).
     25- Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed.
     26- Optical bench and access to the clean tent.
    2627
    2728**Date performed and by whom**
    2829
    29 **Comments**