P1.3 Installation of SHARK-NIR HW and electronics in clean room

  • Phase : 1
  • Status : Draft
  • Category : Unpack, Assemble, and Verification (C1)
  • Recurrence : once
  • Duration : 1.5 day

Description

  • Install and integrate the different SHARK-NIR opto-mechanical components onto the mechanical structure. Install the electronics cabinets. Move the unit to the cleanroom.

Prerequisites

  • All the necessary tools and safety features to do the installation, integration, and moving to the cleanroom. The mechanical structure to hold SHARK-NIR at the cleanroom should be assembled and ready to be used (with the possibility to move to the cleanroom).

Procedure

  • Carefully integrate the cryostat unit with the derotator-optical bench unit.
  • Before installing the motor electronics rack in the cleanroom, take it to the LBT Platform cabinet (its final destination) shared with iLocater for sanity checks.
  • Set up the electronics racks.

Templates

Success criteria

  • The SHARK-NIR is primarily assembled on to the mechanical structure.
  • Electronics racks are set up and ready to use.

Notes

LBTO support

  • Crane operator to lift and move stuff (mountain bay and/or cleanroom).
  • 1-2 crew to support installation procedure (mountain bay and/or cleanroom).
  • Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed.
  • Optical bench and access to the clean tent.