Changes between Version 11 and Version 12 of docs/CommissioningPlan/P1.3
- Timestamp:
- 01/28/21 15:44:33 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P1.3
v11 v12 11 11 **Procedure** 12 12 • Carefully integrate the cryostat unit with the derotator-optical bench unit. 13 * Before installing the motor electronics rack in the cleanroom, take it to the LBT Platform cabinet (its final destination) shared with iLocat or for sanity checks.13 * Before installing the motor electronics rack in the cleanroom, take it to the LBT Platform cabinet (its final destination) shared with iLocater for sanity checks. 14 14 • Install the electronics cabinet. 15 15 **Success criteria** … … 22 22 • 1-2 crew to support installation on the mechanical structure. 23 23 * Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed. 24 * Optical bench and access to clean tent. 24 25 **Associated SHARK-NIR personnel** 25 26 … … 28 29 **Comments** 29 30 30 LM: we have to discuss this internally, because some of the procedures are not clear to me. It is called iLocatEr, not iLocatOr. LBTO support should include providing an optical bench and the clean tent 31 LM: we have to discuss this internally, because some of the procedures are not clear to me. It is called iLocatEr, not iLocatOr. LBTO support should include providing an optical bench and the clean tent [DISCUSS]