wiki:docs/CommissioningPlan/P1.3

Version 11 (modified by lmarafatto, 4 years ago) (diff)

--

P1.3 Complete the installation of SHARK-NIR in the cleanroom with its electronics cabinet

  • Phase : 1
  • Status : Draft
  • Category : Unpack, Assemble, Verification, and Installation (C1)
  • Recurrence : once
  • Duration : half a day

Description

  • Install and integrate the different SHARK-NIR opto-mechanical components onto the mechanical structure. Install the electronics cabinets. Move the unit to the cleanroom.

Prerequisites

  • All the necessary tools and safety features to do the installation, integration, and moving to the cleanroom. The mechanical structure to hold SHARK-NIR at the cleanroom should be assembled and ready to be used (with the possibility to move to the cleanroom).

Procedure

  • Carefully integrate the cryostat unit with the derotator-optical bench unit.
  • Before installing the motor electronics rack in the cleanroom, take it to the LBT Platform cabinet (its final destination) shared with iLocator for sanity checks.
  • Install the electronics cabinet.

Success criteria

  • The SHARK-NIR is primarily assembled on to the mechanical structure.
  • Electronics cabinets are installed.

Notes

LBTO support

  • Crane operator to lift and move stuff.
  • 1-2 crew to support installation on the mechanical structure.
  • Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed.

Associated SHARK-NIR personnel

Date performed and by whom

Comments

LM: we have to discuss this internally, because some of the procedures are not clear to me. It is called iLocatEr, not iLocatOr. LBTO support should include providing an optical bench and the clean tent