    1 == P1.2 Opening boxes and their visual inspection ==
     1== P1.2 Opening boxes, their visual inspection, and mounting the units on the handling ==
    22•       **Phase**               :       1 
    33•       **Status**              :       Draft   
    44•       **Category**            :       Unpack, Assemble, Verification, and Installation (C1)
    55•       **Recurrence**  :       once
    6 •       **Duration**            :       half a day
     6•       **Duration**            :       1 day
    77**Description**
    88•       Unpack the containers/boxes carefully and visually inspect the components inside
     
    1313•       Visually inspect if all the contents are safe and secure.
    1414•       Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).
    15 * Move all needed box contents to the cleanroom. This may require some mounting or handling structures.
     15* Set up the handlings for the cyostat and the optical bench. install the corresponding onto the handling and move to the cleanroom.
     16
    1617**Success criteria**
    1718•       No damage to any container or boxes.
     
    2728**Comments**
    2829
    29 MB:I would add to move all needed box contents in the clean room. This requires probably some mounting, e.g. of the shark-nir handling used to keep the instrument while integrating cryostat and then making tests [DONE. this is also there in the next activity. maybe we don't need it here]