P1.2 Opening boxes, their visual inspection, and mounting the units on the handling
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, Verification, and Installation (C1)
- Recurrence : once
- Duration : 1 day
Description
- Unpack the containers/boxes carefully and visually inspect the components inside
Prerequisites
- All the necessary tools and safety features to do the unpacking and moving.
Procedure
- Carefully unpack the containers/boxes containing the SHARK-NIR opto-mechanical components.
- Visually inspect if all the contents are safe and secure.
- Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).
- Set up the handlings for the cyostat and the optical bench. install the corresponding onto the handling and move to the cleanroom.
Success criteria
- No damage to any container or boxes.
Notes
LBTO support
- Crane operator to lift and move stuff.
- 1-2 crew to support unpacking and moving.
Associated SHARK-NIR personnel
Date performed and by whom
Comments