    11== P1.2 Opening of boxes in LBT Hall, inspection of the contents and installation on units on their handlings ==
     2
    23- **Phase** :   1 
    34- **Status** :  Draft   
     
    56- **Recurrence** :      once
    67- **Duration** :        1 day
     8
    79**Description**
    810- Unpack the containers/boxes carefully and visually inspect the components inside
     11
    912**Prerequisites**
    1013- All the necessary tools and safety features to do the unpacking and moving. 
     14
    1115**Procedure**
    1216- Carefully unpack the containers/boxes containing the SHARK-NIR opto-mechanical components.
     
    1519- Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).
    1620- Set up the handlings for the cryostat and the optical bench. install the corresponding onto the handling and move to the cleanroom.
     21
    1722**Templates**
    1823
     
    2025- No damage to any container or boxes.
    2126- No shock sensors activated.
     27
    2228**Notes**
    2329
     
    2531- Crane operator (mountain bay) to lift and move stuff.
    2632- 1-2 crew to support unpacking and moving.
     33
    2734**Date performed and by whom**
    2835