P1.2 Opening of boxes in LBT Hall, inspection of the contents and installation on units on their handlings
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, and Verification (C1)
- Recurrence : once
- Duration : 1 day
Description
- Unpack the containers/boxes carefully and visually inspect the components inside
Prerequisites
- All the necessary tools and safety features to do the unpacking and moving.
Procedure
- Carefully unpack the containers/boxes containing the SHARK-NIR opto-mechanical components.
- Visually inspect if all the contents are safe and secure.
- Inspect if the tilt and shock sensors are activated or not.
- Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).
- Set up the handlings for the cryostat and the optical bench. install the corresponding onto the handling and move to the cleanroom.
Templates
Success criteria
- No damage to any container or boxes.
- No shock sensors activated.
Notes
LBTO support
- Crane operator (mountain bay) to lift and move stuff.
- 1-2 crew to support unpacking and moving.
Date performed and by whom