    1 == P1.2 Opening boxes, their visual inspection, and mounting the units on the handling ==
    2 •       **Phase**               :       1 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Unpack, Assemble, and Verification (C1)
    5 •       **Recurrence**  :       once
    6 •       **Duration**            :       1 day
     1== P1.2 Opening of boxes in LBT Hall, inspection of the contents and installation on units on their handlings ==
     2- **Phase** :   1 
     3- **Status** :  Draft   
     4- **Category** :        Unpack, Assemble, and Verification (C1)
     5- **Recurrence** :      once
     6- **Duration** :        1 day
    77**Description**
    8 •       Unpack the containers/boxes carefully and visually inspect the components inside
     8- Unpack the containers/boxes carefully and visually inspect the components inside
    99**Prerequisites**
    10 •       All the necessary tools and safety features to do the unpacking and moving. 
     10- All the necessary tools and safety features to do the unpacking and moving. 
    1111**Procedure**
    12 •       Carefully unpack the containers/boxes containing the SHARK-NIR opto-mechanical components.
    13 •       Visually inspect if all the contents are safe and secure.
    14 * Inspect if the tilt and shock sensors are activated or not.
    15 •       Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).
    16 * Set up the handlings for the cryostat and the optical bench. install the corresponding onto the handling and move to the cleanroom.
     12- Carefully unpack the containers/boxes containing the SHARK-NIR opto-mechanical components.
     13- Visually inspect if all the contents are safe and secure.
     14- Inspect if the tilt and shock sensors are activated or not.
     15- Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).
     16- Set up the handlings for the cryostat and the optical bench. install the corresponding onto the handling and move to the cleanroom.
     17**Templates**
    1718
    1819**Success criteria**
    19 •       No damage to any container or boxes.
    20 * No shock sensors activated.
     20- No damage to any container or boxes.
     21- No shock sensors activated.
    2122**Notes**
    2223
    2324**LBTO support**
    24 •       Crane operator (mountain bay) to lift and move stuff.
    25 * 1-2 crew to support unpacking and moving.
    26 **Associated SHARK-NIR personnel**
    27 •       
     25- Crane operator (mountain bay) to lift and move stuff.
     26- 1-2 crew to support unpacking and moving.
    2827**Date performed and by whom**
    2928
    30 **Comments**