     1== P1.2 Opening boxes and their visual inspection ==
     2•       **Phase**               :       1 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Installation, integration, verification (C1)                           
     5•       **Recurrence**  :       once
     6•       **Duration**            :       1 hour(s)
     7**Description**
     8•       Unpack the containers/boxes carefully and visually inspect the components inside
     9**Prerequisites**
     10•       All the necessary tools and safety features to do the unpacking and moving. 
     11**Procedure**
     12•       Carefully unpack the containers/boxes containing the SHARK-NIR opto-mechanical components.
     13•       Visually inspect if all the contents are safe and secure.
     14•       Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).
     15**Success criteria**
     16•       No damage to any container or boxes.
     17**Notes**
     18**LBTO support**
     19•       Crane operator to lift and move stuff.
     20•       1-2 crew to support unpacking and moving.
     21**Associated SHARK-NIR personnel**
     22•       JF, LM, MdP,
     23**Date performed and by whom**