| 1 | == P1.2 Opening boxes and their visual inspection == |
| 2 | • **Phase** : 1 |
| 3 | • **Status** : Draft |
| 4 | • **Category** : Installation, integration, verification (C1) |
| 5 | • **Recurrence** : once |
| 6 | • **Duration** : 1 hour(s) |
| 7 | **Description** |
| 8 | • Unpack the containers/boxes carefully and visually inspect the components inside |
| 9 | **Prerequisites** |
| 10 | • All the necessary tools and safety features to do the unpacking and moving. |
| 11 | **Procedure** |
| 12 | • Carefully unpack the containers/boxes containing the SHARK-NIR opto-mechanical components. |
| 13 | • Visually inspect if all the contents are safe and secure. |
| 14 | • Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed). |
| 15 | **Success criteria** |
| 16 | • No damage to any container or boxes. |
| 17 | **Notes** |
| 18 | **LBTO support** |
| 19 | • Crane operator to lift and move stuff. |
| 20 | • 1-2 crew to support unpacking and moving. |
| 21 | **Associated SHARK-NIR personnel** |
| 22 | • JF, LM, MdP, |
| 23 | **Date performed and by whom** |