P1.2 Opening boxes and their visual inspection
- Phase : 1
- Status : Draft
- Category : Installation, integration, verification (C1)
- Recurrence : once
- Duration : 1 hour(s)
Description
- Unpack the containers/boxes carefully and visually inspect the components inside
Prerequisites
- All the necessary tools and safety features to do the unpacking and moving.
Procedure
- Carefully unpack the containers/boxes containing the SHARK-NIR opto-mechanical components.
- Visually inspect if all the contents are safe and secure.
- Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).
Success criteria
- No damage to any container or boxes.
Notes LBTO support
- Crane operator to lift and move stuff.
- 1-2 crew to support unpacking and moving.
Associated SHARK-NIR personnel
- JF, LM, MdP,
Date performed and by whom