wiki:docs/CommissioningPlan/P1.1

Version 15 (modified by kradhakrishnan, 3 years ago) (diff)

--

P1.1 Inspection of the closed boxes

  • Phase : 1
  • Status : Draft
  • Category : Unpack, Assemble, and Verification (C1)
  • Recurrence : once (when SHARK-NIR reaches LBT)
  • Duration : 0.5 day

Description

  • Visual inspection of all the SHARK-NIR containers and boxes at the LBT mountain bay

Prerequisites

  • All the SHARK-NIR containers and boxes should be at LBT mountain bay

Procedure

  • Visually inspect if all the SHARK-NIR containers and boxes at the LBT mountain bay are safe and secure.
  • Inspection of the state of tilt and shock sensor.
  • Check if there is any damage to any part of the shipment. If yes, note them, take photos, and communicate to the respective insurance party (if needed).

Templates

Success criteria

  • No damage to any container or boxes.
  • No shock sensors activated.

Notes

  • See AD10 for more details.

LBTO support

  • Crane operator (mountain bay) to lift and move stuff.
  • 1-2 crew to support moving containers/boxes.

Date performed and by whom