    11== P1.1 Inspection of the closed boxes ==
    22
    3 •       **Phase**               :       1 
    4 •       **Status**              :       Draft
    5 •       **Category**            :       Unpack, Assemble, and Verification (C1)
    6 •       **Recurrence**  :       once (when SHARK-NIR reaches LBT)
    7 •       **Duration**            :       half a day
     3- **Phase**             :       1 
     4- **Status**            :       Draft
     5- **Category**          :       Unpack, Assemble, and Verification (C1)
     6- **Recurrence**        :       once (when SHARK-NIR reaches LBT)
     7- **Duration**          :       half a day
     8
    89**Description**
    910- Visual inspection of all the SHARK-NIR containers and boxes at the LBT mountain bay
     11
    1012**Prerequisites**
    1113- All the SHARK-NIR containers and boxes should be at LBT mountain bay
     14
    1215**Procedure**
    1316- Visually inspect if all the SHARK-NIR containers and boxes at the LBT mountain bay are safe and secure.
     
    2023- No damage to any container or boxes.
    2124- No shock sensors activated.
     25
    2226**Notes**
    2327
     
    2529- Crane operator (mountain bay) to lift and move stuff.
    2630- 1-2 crew to support moving containers/boxes.
     31
    2732**Date performed and by whom**