     1== P1.12 Testing of SCICAM image grabbing by SOUL-AO ==
     2•       **Phase**               :       1 
     3•       **Status**              :       Draft
     4•       **Category**            :       Unpack, Assemble, and Verification (C1)
     5•       **Recurrence**  :       once
     6•       **Duration**            :       2 days
     7**Description**
     8•       Testing the SCICAM imaging grabbing (from a repository/folder) by SOUL-AO which is a pre-requisite for the SOUL-AO optimization for SHARK-NIR
     9**Prerequisites**
     10•       ICE compatibility between SHARK-NIR and SOUL-AO system
     11* SCICAM image should have a header following FITS standard
     12**Procedure**
     13•       Save a SCICAM image (with a PSF image) on the agreed folder or repository
     14•       Check if SOUL-AO can grab the image and analyze the PSF
     15**Success criteria**
     16•       SOUL-AO SW can grab the SCICAM image
     17**Notes**
     18The time dedicated to this activity has to be considered in combination with the other activities if needed. Parallelism is possible.
     19* Points of contact: Alfio and Fabio from Arcetri
     20
     21**LBTO support**
     22
     23* LBTO SW support may be required
     24
     25**Associated SHARK-NIR personnel**
     26
     27**Date performed and by whom**