Changes between Version 2 and Version 3 of docs/CommissioningActivityList
- Timestamp:
- 03/04/20 14:36:57 (5 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningActivityList
v2 v3 34 34 == Phase 1 == 35 35 36 || {{{Number}}}||{{{Activity Name}}}||{{{Day/Night}}}||{{{Duration(mins)}}}||{{{Maximum Duration(mins)}}}||{{{Category}}}||{{{LBTO Support}}}||{{{SHARK-NIR Location}}}||36 ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (mins)'''||'''Maximum Duration (mins)'''||'''Category'''||'''LBTO Support'''||'''SHARK-NIR Location'''|| 37 37 ||P1.1||Inspection of the boxes||Day||40||40||C1||-||mountain bay|| 38 38 ||P1.2||Opening boxes and their visual inspection||Day||60||60||C1||crane operator to lift and move containers/boxes, 1-2 crew to support unpacking and moving||mountain bay|| … … 44 44 ||P1.8||Verification of the internal alignment of the instrument||Day||120||120||C1||-||clean room|| 45 45 ||P1.9||Science detector calibrations||Day||60||60||C1||-||clean room|| 46 46 47 == Phase 2 == 47 48