wiki:docs/CommissioningActivityList

Version 2 (modified by kradhakrishnan, 5 years ago) (diff)

--

SHARK-NIR Commissioning Activities List

This is an evolving page and the lists and activities will evolve in time as we gain more and more experience.

Although it is mentioned as the commissioning activities list, it lists all the activities of SHARK-NIR from its unpacking at LBT till the Science Verification, with the exception of the instrument installation at the LBT Bent Gregogian Central focal station.

The commissioning is broadly divided into 3 Phases:

Phase 1: We start from inspecting the boxes at LBT mountain bay, unpacking and installing the instrument at the mountain lab for alignment verification and functionality checks. All of these are daytime activities.

Phase 2: The activities after the installation of SHARK-NIR at the SX central bent Gregorian focus of LBT to the acquirement of the first nighttime telescope collimation model of the instrument form the Phase 2. Most of the activities are daytime. The only nighttime activity is to check the pointing, acquisition sequence and getting the first nighttime telescope collimation model for SHARK-NIR.

Phase 3: Phase 3 of the commissioning starts from sending preset to the telescope to testing individual SHARK-NIR observation modes for performance to the total SHARK-NIR performance. All the activities are nighttime. By the end of this phase, SHARK-NIR is ready for Science Verification.

Note that the corresponding evolving doc in SHARK-NIR Dropbox folder is SHARK-NIR Commissioning Plan with document number SHARK-NIR-INAFP-COM-001.

Applicable Documents

No. Title Number & Issue
AD1 SHARK-NIR Schedule SHARK-NIR-INAFP-Schedule-FDR Issue 0.3
AD2 SHARK-NIR SW ICD SHARK-NIR-INAFP-SW-ICD-FDR Issue 0.4
AD3 SHARK-NIR Installation Plan SHARK-NIR-INAFP-IP-001 Issue 0.1
AD4 SHARK-NIR Calibrations SHARK-NIR-INAFP-MAN-004

Category

The table below lists the categories of commissioning activities.

Category NameCategory Number
Installation, integration, verification C1
Daytime testing (functionality and operability)C2
Daytime calibrationC3
Nighttime testing (functionality and operability)C4
Nighttime calibrationC5
Nighttime testing for performanceC6

Phase 1

NumberActivity NameDay/NightDuration(mins)Maximum Duration(mins)CategoryLBTO SupportSHARK-NIR Location
P1.1Inspection of the boxesDay4040C1-mountain bay
P1.2Opening boxes and their visual inspectionDay6060C1crane operator to lift and move containers/boxes, 1-2 crew to support unpacking and movingmountain bay
P1.3Install the instrument in the cleanroom with its electronics cabinetDay240240C1crane operator to lift and move containers/boxes, 1-2 crew to support installation on the mechanical structuremountain bay + clean room
P1.4Cable in the instrument, power on, and connect to LBT networkDay120120C1support to connect to LBT network? Any electronics support?clean room
P1.5Start all the services and initialize all the motorsDay2020C1-clean room
P1.6Cool down the cryostatDay480480C1Liquid N2 fillclean room
P1.7Verification of the operability of the motors and light sourcesDay6060C1-clean room
P1.8Verification of the internal alignment of the instrumentDay120120C1-clean room
P1.9Science detector calibrationsDay6060C1-clean room

Phase 2

Phase 3

Additional Information