Changes between Version 88 and Version 89 of docs/CommissioningPlan


Ignore:
Timestamp:
01/19/21 11:17:42 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v88 v89  
    7373
    7474== Commissioning Activity ==
    75 In this section, you can see all the commissioning activities listed in chronological order. If you click the individual activity, you can see more details of it.
     75In this section, you can see all the commissioning activities listed in chronological order. If you click the individual activity, you can see more details of it. 8 hours is considered as the duration of day/night.
    7676
    7777=== Phase 1 (Pre-commissioning)===
     
    104104||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day||3||C2 + C3||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation||
    105105||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Cryostat warm up check]||Day||2||C2||-||
    106 ||Total||Contigency included within || ||27 days || || ||
     106||Total||Contingency included within || ||35 days || || ||
    107107
    108108