docs/CommissioningPlan
v85 v86 101 101 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||5+5||C2 + C3||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO|| 102 102 ||P2.xx||[wiki:/docs/CommissioningPlan/P2.xx Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||3||C2||Mounting RR on the SX side. Support on running SOUL AO|| 103 ||P2. 7||[wiki:/docs/CommissioningPlan/P2.7Looking for filter defects/effects/features+ Science detector calibrations repeat]||Day||2||C2||Mounting RR on the SX side. Support on running SOUL AO||103 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Looking for filter defects/effects/features+ Science detector calibrations repeat]||Day||2||C2||Mounting RR on the SX side. Support on running SOUL AO|| 104 104 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day||3||C2 + C3||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation|| 105 105 ||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Cryostat warm up check]||Day||2||C2||-||