    102102||P2.xx||[wiki:/docs/CommissioningPlan/P2.xx Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||3||C2||Mounting RR on the SX side. Support on running SOUL AO||
    103103||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features+ Science detector calibrations repeat]||Day||2||C2||Mounting RR on the SX side. Support on running SOUL AO||
    104 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Flexure tests]||Day||3||C2 + C3||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation||
    105 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Cryostat warm up check]||Day||2||C2||-||
     104||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day||3||C2 + C3||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation||
     105||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Cryostat warm up check]||Day||2||C2||-||
    106106||Total||Contigency included within || ||27 days || || ||