Changes between Version 83 and Version 84 of docs/CommissioningPlan
- Timestamp:
- 01/19/21 10:52:29 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v83 v84 99 99 ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||2+1||C2||working platform installed in front of the Gregorian focal-station SX, Mounting RR on the SX side. Support on running SOUL AO|| 100 100 ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||5||C2||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. If not Argos swing arm, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team on running SOUL AO|| 101 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA (baseline, phase-diversity, Woll+DI-DBI+ARGOS swing-arm)]||Day||5+5||C2 + C3||Mounting RR on the SX side. Support on runningSOUL AO||101 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||5+5||C2 + C3||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO|| 102 102 ||P2.xx||[wiki:/docs/CommissioningPlan/P2.xx Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||3||C2||Mounting RR on the SX side. Support on running SOUL AO|| 103 103 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features+ Science detector calibrations repeat]||Day||2||C2||Mounting RR on the SX side. Support on running SOUL AO||